Here are all news and milestones listed.
26.11.2006
Upper Forward Fuselage Assembly
started.
12.11.2006
Step Installation
started (and finished three days later)
30.10.2006
1000 Hours reached.
24.10.2006
Engine bought on EBay
21.10.2006
Fwd. Fuse Ribs & Skins
finished.
12.10.2006
Fuse Side Skins
started.
14.09.2006
Wingtips
finished.
01.09.2006
Flaps
finished
31.08.2006
Ailerons
finished.
28.08.2006
Inspection of flaps and ailerons: passed!
19.08.2006
Fwd Fuse Ribs & Skins
started
22.07.2006
Mid Fuse Ribs&Skins
finished.
13.07.2006
Tanks
finished: Both tanks sealed!.
25.06.2006
Firewall
started.
11.06.2006
Mid Fuse Bulkheads
finished.
04.06.2006
Mid Fuse Ribs&Skins
started.
22.05.2006
Mid Fuse Bulkheads
started.
11.05.2006
Arrival of
Fuselage
.
30.03.2006
Wing Tips
started.
23.03.2006
Aileron Actuation
started.
04.02.2006
Tanks
started.
02.01.2006
Ailerons
started.
20.12.2005
first Anniversary
05.12.2005
500 hours reached.
06.06.2005
Elevators
done: 73.75h
04.06.2005
Horizontal Stabilizer
done: 64.25h
31.05.2005
Inspection of
Horizontal Stabilizer
and
Elevators
done.
26.05.2005
Wings
started
30.04.2005
200 hours build time reached
28.03.2005
Tailcone
started
20.03.2005
Horizontal Stabilizer
ready for inspection
26.02.2005
Elevators
started
18.02.2005
Rudder
done! 31h
12.02.2005
Vertical Stabilizer
done! 28.25 h
31.01.2005
Updated Empennage pages
Vertical Stabilizer
,
Rudder
and
Horizontal Stabilizer
27.12.2004
Vertical Stabilizer ready for priming
20.12.2004
Christmas was four days too early. Empennage and Wing kit arrived.
01.12.2004
Empennage and Wing Kit scheduled to arrive 16.12.
Copyright © 2004-2007 Lorenz Malmström